Home
Deck Building Deck Repair Composite Decking Deck Staining Covered Decks Screened Porches
About FAQ Contact Call (470) 888-6871
Wood deck boards running away from the camera beside a curved rail

Deck Building in South Fulton, GA

New decks designed around your yard's grade and soil, permitted through the city, and framed so the connections outlast the boards on top of them.

At a Glance

What the Rules actually require on a South Fulton deck

ElementRequirement
Pier depth12 inches minimum into undisturbed soil, bearing on firm soil. Fill only with a Georgia registered engineer's design.
Ledger board2x8 minimum, no smaller than the joists, and never fastened to stone or masonry veneer.
Ledger flashingCorrosion-resistant metal, 0.019 inch minimum thickness, lapped so water cannot reach the band joist.
Ledger fastenersThrough-bolts or approved structural screws. Framing nails and deck screws do not qualify.
Lateral hold-downsTwo devices rated at least 1,500 pounds within 24 inches of each end.
Guard height36 inches minimum above the walking surface, with openings that will not pass a 4-inch sphere.
Guard strength200 pounds applied horizontally at any point along the top rail.
Stair geometry7-3/4 inch maximum riser, 10 inch minimum tread, and no more than 3/8 inch variation within one flight.
HandrailRequired at four or more risers, mounted 34 to 38 inches above the nosing line.
Joist spacing16 inches on center for most decking, 12 inches under diagonal composite layouts.
Fastener metalHot-dip galvanized or stainless in contact with treated lumber, matched to the connectors.
Wood deck boards running away from the camera beside a curved rail Wood table and a weathered deck rail looking out over green hills
12"Pier Depth

What Does Building a New Deck in South Fulton Involve?

It starts on paper. A new deck needs a site plan approved by the Planning Department before the city will issue a permit, and the application goes through the SagesGov portal. Then the yard decides the rest. We set pier locations off the grade and the soil, dig a minimum of twelve inches into undisturbed ground, and hold the footing inspection before any concrete is poured. From there it is ledger and flashing, beams and joists, then decking, guards, and stairs, with a framing inspection before the deck boards cover anything up. Final inspection closes the permit out. Most of the schedule risk sits in plan review, not in the building.

  • Site plan and permit
  • Grade-driven pier layout
  • Footing inspection first
  • Flashed ledger detail
  • Code guards and stairs
  • Permit closed at final

How a New Deck Gets Built Here

Design and paperwork first, then four site stages with two inspection gates in the middle.

1

Walk and Design

We measure the yard, check grade and access, and lay out pier positions against where the ledger can actually land.

2

Plan and Permit

Site plan to the Planning Department, then the permit application through the city's SagesGov portal.

3

Footings and Frame

Piers dug a foot into undisturbed soil, inspected before the pour, then ledger, beams, and joists.

4

Deck and Final

Boards, guards, and stairs after the framing inspection, then final inspection closes the permit.

Why Us

Six Things we do not skip on a South Fulton build

None of this is exotic and none of it is expensive relative to the job. It is simply the list a rushed crew works through last, and the list an inspector works through first.

Piers into undisturbed soil, not fill

The city's deck handout is specific: 12 inches minimum, bearing on firm soil. Loose backfill from the original house build does not count as ground.

A ledger detail you could photograph

Through-bolted or structural-screwed on the code's schedule, flashed with corrosion-resistant metal, and kept off any brick or stone veneer.

Lateral hold-downs actually installed

The tension devices that stop a deck pulling away from the house sideways. Small hardware, cheap, and the first thing a budget bid leaves out.

Joist tape before the boards go down

A butyl membrane over joists, beams, and the ledger. It seals around every fastener hole, which is precisely where substructure rot starts.

Guards and stairs measured, not eyeballed

36 inch guards, the 4-inch sphere rule, risers within 3/8 inch of each other across the flight. The bottom step is where most flights fail.

The permit run properly

Site plan to Planning, application through SagesGov, permit card posted, inspections requested by email with the permit number attached.

Why the City Wants a Foot of Undisturbed Soil

Georgia's frost line is shallow, so the twelve inch rule is not about frost. It is about what Piedmont red clay does across a wet and dry year.

  • The soilPiedmont red clay is expansive. It swells when it takes on water and shrinks back as it dries, and it does that seasonally rather than once.
  • The failureA pier sitting shallow or on backfill rides that movement. The deck racks, the boards open unevenly, and an attached deck pushes that movement into the house framing.
  • The ruleTwelve inches into undisturbed soil, bearing on firm soil, per the City of South Fulton deck handout. Fill is only acceptable when a Georgia registered engineer designs for it.
  • The inspectionFootings are inspected once the piers are dug and before any concrete goes in. That is the only moment anyone can verify this, which is why it is a hold point.
  • The tellIf a bid does not state a pier depth, ask. It is the cheapest thing to shortchange and the most expensive thing to correct later.
Service Area

Deck Work Across South Fulton and Nearby

We cover all 92 square miles of South Fulton plus the towns around it, out to Palmetto and Chattahoochee Hills on one side, Riverdale and Fayetteville on the other. If your mail still says Atlanta, Fairburn, or Union City, you are almost certainly inside our area. No travel charge inside that ring.

South Fulton Fairburn Union City East Point College Park Palmetto Chattahoochee Hills Hapeville Riverdale Douglasville Fayetteville Tyrone Newnan Peachtree City Jonesboro Forest Park Lithia Springs Atlanta
Questions

New Deck questions from South Fulton homeowners

Pressure-treated typically runs about $25 to $45 per square foot installed across the Atlanta metro, and capped composite about $35 to $60. Those are ranges, not a quote. Height above grade, stair flights, linear feet of railing, and access to the back yard move a real price more than the deck's area does.
Yes. New decks and replacements require a permit and inspections, and a new deck also needs a site plan approved by the Planning Department before the permit can issue. The application is filed through the city's SagesGov portal.
The current Georgia residential code as adopted statewide, plus what the City of South Fulton enforces at plan review. Deck framing, guards, and ledger provisions all live inside it, and composite decking additionally follows the manufacturer's published instructions.
16 inches on center covers most wood and most straight-run composite. Diagonal layouts and some commercial-grade composite drop to 12 inches, because turning the boards 45 degrees increases the effective span between bearing points.
Not to the veneer. Code bars supporting a ledger on stone or masonry veneer, because veneer is cladding and cannot carry deck load. On a brick house the options are attaching through to the structure properly or building the deck freestanding on its own posts.
It is a pair of tension devices that keep the deck from pulling away from the house sideways. Code calls for two rated at least 1,500 pounds within 24 inches of each end, or a four-device alternative at 750 pounds each. Decks no more than 30 inches above grade are treated differently.
Plan review is usually the long pole. Once the permit is in hand, a straightforward rectangular deck is a matter of days and a multi-level or heavily railed one is a couple of weeks, paced by the footing and framing inspections.

Ready to Talk About Your Deck?

Send the address and a photo, or call and we will set a walkthrough. You get one written price, the permit handled, and a start date you can plan around.

(470) 888-6871
Mon to Sat, 7am to 6pm
Call Now
Call (470) 888-6871